WEEK OF DECEMBER 16, 2019

Traffic impacts during some pavement repairs will effect Masonic Home Road with alternative travel allowed in both directions through the work zone. Detail officers will be available at either end of the work zone assisting people, school buses, daily deliveries and sanitary services.

Work will not take place on Christmas Day and will conclude for the year on Friday, Dec. 27, 2019. In the spring, road reconstruction will commence.

From all of us on the Charlton waterline project, we thank you for your patience this year during this important project and wish every a happy holiday season.

WEEK OF DECEMBER 2, 2019

Traffic impacts will effect Old Worcester Road by the cow tunnel, with traffic detoured in both directions. Detail officers will be available at either end of the work zone assisting people, school buses, daily deliveries and sanitary services.

WEEK OF NOVEMBER 4, 2019

Traffic impacts will effect Muggett Hill Road to relocate a fire hydrant, with the road closed between 8:45 a.m. to 1:45 p.m. to avoid school bus impacts. Detail officers will be available at either end of the work zone assisting people, school buses, daily deliveries and sanitary services.

Water main work will effect Morton Station Road, with work detoured in both directions with buses allowed to pass through the work zone.

Detail officers will be available at either end of the work zone assisting people, school buses, daily deliveries and sanitary services.

Charlton Waterline Planned Work: Weeks of November 4, 2019 – November 15, 2019

WEEK OF OCTOBER 7, 2019

Traffic impacts will continue to effect Old Worcester Road, with traffic detoured in both directions. Additionally, a culvert will be replaced resulting in a road closure between Morton Station Road and Main Street. Detail officers will be available at either end of the work zone assisting people, school buses, daily deliveries and sanitary services.

Charlton Waterline Planned Work: Weeks of October 7, 2019 – October 18, 2019

WEEK OF SEPTEMBER 23, 2019

Traffic impacts will continue to effect Old Worcester Road. Detail officers will be available at either end of work zones assisting people, school buses, daily deliveries and sanitary services.

Charlton Waterline Planned Work: Weeks of September 23, 2019 – October 4, 2019

WEEK OF SEPTEMBER 9, 2019

Traffic impacts related to the Charlton Waterline work will continue to effect Old Worcester Road, H. Putnam Road, Morton Station Road, and Muggett Hill Road.

Detail officers will be available at either end of work zones assisting people, school buses, daily deliveries and sanitary services. All work is coordinated with the schools.

Charlton Waterline Planned Work: Weeks of September 9, 2019 – September 20, 2019

WEEK OF AUGUST 26, 2019

H. Putnam Road water main connection to Route 20 may be completed, upon which the traffic will be shifted around the work zone.

Morton Station Road water main work will continue with traffic detoured in both directions. Only school buses that are picking up students on Morton Station Road will be allowed to pass, and all work is being coordinated directly with the schools.

Muggett Hill Road water main work continues with some water services continuing from the water main to the property lines. Muggett Hill Road will be closed to through traffic between 8:45 a.m. and 1:45 p.m., allowing only local residents, daily deliveries and sanitation services with traffic detoured in both directions.

Detail officers will be posted at each work zone assisting vehicles, people, school buses, daily deliveries and sanitary services to properties.

Charlton Waterline Planned Work: Weeks of August 26, 2019 – September 6, 2019

WEEK OF AUGUST 12, 2019

H. Putnam Road water connection to Route 20 may be completed, upon which the traffic will be shifted around the work zone by detail officers.

Heritage Access Roads and Muggett Hill Road water main work will continue with traffic detoured in both directions. The crew is also at middle school driveway making the connection to Oxford Road. Detail officers are at each end of the work zone assisting people, school buses, daily deliveries and sanitary services to access properties.

Dodge Lane water main installation is scheduled through August 16, and due to the narrow width, the construction zone is expected to occupy the entire roadway. Residents will be notified in person ahead of time should special needs, such as off-site vehicle staging, be required. Detail officers will be at the each end of the work zone assisting people.

Charlton Waterline Planned Work: Weeks of August 12, 2019 – August 23, 2019

WEEK OF JULY 29, 2019

H. Putnam Road water main connection to Route 20 shall be completed. Traffic will be shifted around the work zones with detail officers assisting traffic at either end of the work zone.

Heritage Access Roads and Muggett Hill Road water main work continues with traffic detoured in both directions. Detail officers are at either side of the work zone assisting people, school buses, deliveries and sanitary services to access properties.

L. Stevens Road water main testing will be conducted allowing the road to be mostly open. Detail officers will be at the end of each work zone assisting with property access.

Charlton Waterline Planned Work: Weeks of July 29, 2019 – August 9, 2019

WEEK OF JULY 12, 2019

The H. Putnam Road water main connection to Route 120 expects to complete and traffic will be shifted around the work zone.

Heritage Access Roads water main construction continues with traffic detoured in both directions. Once the crew is finished with the connector road, they will open the connector road and start at the back of the middle school and work towards Muggett Hill Road.

Muggett Hill Road work expects to begin with traffic detoured in both directions. Water services will continue in the same work zone.

Small crews will be testing the water mains and services recently installed along Masonic Home Road.

Road requiring detours will provide detail officers at each end of the work zone to assist people, school buses, daily deliveries and sanitary services.

The map below depicts impacted roads (orange), work zones (red), and suggested travel routes during construction (green).

Charlton Waterline Planned Work: Weeks of July 15, 2019 – July 26, 2019

WEEK OF JULY 1, 2019

With water main work complete, crews will begin water main pressure testing on L. Stevens Road.

Water main work will continue on Heritage Access Road and Muggett Hill Road with traffic detoured in both directions. Detail officers are at each end of the work zones assisting people, school buses, daily deliveries, and sanitary services to access properties.

Small work crews will be working sporadically on Masonic Home Road and may require alternative traffic on one lane.

The map below depicts impacted roads (orange), work zones (red), and suggested travel routes during construction (green).

*HOLIDAY NOTE: Work will cease on July 4 and July 5 in honor of Independence Day.

Charlton Waterline Planned Work: Weeks of July 1, 2019 – July 12, 2019

WEEK OF JUNE 17, 2019

The map below depicts impacted roads (orange), work zones (red), and suggested travel routes during construction (green).

Work continues on L. Stevens Road, Heritage Access Road, Old Muggett Hill Road, and Muggett Hill Road with traffic detoured in both directions. Detail officers are at each end of the work zones assisting people, school buses, daily deliveries, and sanitary services to access properties.

Small work crews will be working sporadically on Masonic Home Road and may require alternative traffic on one lane.

The map below depicts impacted roads (orange), work zones (red), and suggested travel routes during construction (green).

Charlton Waterline Planned Work: Weeks of June 17, 2019 – June 28, 2019

WEEK OF JUNE 3, 2019

Work continues on Old Worcester Road, Old Muggett Hill Road, L. Stevens Road and Morton Station Road with traffic detoured in both directions. Detail officers are at each end of the work zones assisting people, school buses, daily deliveries and sanitary services to access properties.

Small work crews will be working sporadically on Masonic Home Road and may require alternative traffic on one lane.

The map below depicts impacted roads (orange), work zones (red), and suggested travel routes during construction (green).

Charlton Waterline Planned Work: Weeks of June 3, 2019 – June 14, 2019

WEEK OF MAY 20, 2019

Work continues on Old Worcester Road, Hammerock Road, L. Turner Road, and Old Muggett Hill Road with traffic detoured in both directions. Detail officers are at each end of the work zones assisting people, school buses, daily deliveries and sanitary services to access properties.

Small work crews will be working sporadically on Masonic Home Road and may require alternative traffic on one lane.

After work completes on Masonic Home Road, water services may begin on L. Putnum Road and L. Stevens Road with traffic detoured in both directions.

The map below depicts impacted roads (orange), work zones (red), and suggested travel routes during construction (green).

Charlton Waterline Planned Work: Weeks of May 20, 2019 – May 31, 2019

WEEK OF MAY 6, 2019

Work continues on Old Worcester Road and H. Putnam Road with traffic detoured in both directions. Detail officers are at each end of the work zones assisting people, school busses, daily deliveries and sanitary services to access properties.

Small crews will be working sporadically on Masonic Home Road. Traffic may be reduced to one lane with two lanes alternating to pass.

Water service work may start on L. Stevens Road after water services are complete on Masonic Home Road with traffic detoured in both directions. Detail officers are at each end of the work zone assisting people, school busses, daily deliveries and sanitary services to access properties.

The map below depicts impacted roads (orange), work zones (red), and suggested travel routes during construction (green).

Charlton Waterline Planned Work: Weeks of May 6, 2019 – May 17, 2019

WEEK OF MARCH 25, 2019

Work resumes on L. Stevens Road and Old Worcester Road with traffic detoured in both directions. Detail officers will be stationed at both ends of the construction zones assisting people, school buses, daily deliveries and sanitary services to properties.

•L. Stevens Road. Work will start by Route 20 and proceed south towards N. Main Street.

•Old Worcester Road. Work will progress south towards Morton Station Road.

•The map below depicts impacted roads (orange), work zones (red), and suggested travel routes during construction (green). IMPACTED ROADS:

Charlton Waterline Planned Work: March 25, 2019 – April 5, 2019

WEEK OF DECEMBER 17, 2018

The Charlton Waterline Project work continues on L. Stevens Road and Old Worcester Road. Water main construction is expected to be completed for the season on Friday, December 21, 2018 and will resume in April 2019.

IMPACTED ROADS:

  • Old Worcester Road: Started early November 2018
  • L. Stevens Road: Started mid-December 2018

TRAFFIC CONTROL MEASURES:

  • The work on Old Worcester Road will continue progressing easterly toward Morton Station Road, while work on L. Stevens Road will start by Route 20 and head south toward N. Main Street.
  • Traffic on Old Worcester Road and L. Stevens Road is being fully detoured. Detail officers are controlling traffic flows from both directions for residents, school busses, daily deliveries and sanitary services to be able to access properties from either side of the work zone.
  • The map below depicts impacted roads (orange), work zones (red), and suggested travel routes during construction (green).

CLICK TO VIEW LARGER MAP

WEEK OF DECEMBER 10, 2018

The Charlton Waterline Project water main construction will cease on Masonic Home Road, continue Old Worcester Road and commence on L. Stevens Road. Water main construction will cease upon the first snow fall and will resume in April 2019.

IMPACTED ROADS:

  • Old Worcester Road: Started early November 2018
  • L. Stevens Road: Starting mid-December 2018

TRAFFIC CONTROL MEASURES:

  • The work on Old Worcester Road will continue progressing easterly toward Morton Station Road.
  • Work commences on L. Stevens Road starting by Route 20 and head south toward N. Main Street.
  • Traffic on Old Worcester Road and L. Stevens Road is being fully detoured. Detail officers are controlling traffic flows from both directions for residents, school busses, daily deliveries and sanitary services to be able to access properties from either side of the work zone.
  • The map below depicts impacted roads (orange), work zones (red), and suggested travel routes during construction (green).

CLICK TO VIEW LARGER MAP

 

WEEK OF DECEMBER 3, 2018

The Charlton Waterline Project water main construction will continue occasionally on Masonic Home Road with traffic detoured in both directions while work on Old Worcester Road is being fully detoured. Water main construction will cease upon the first snow fall and will resume in April 2019.

IMPACTED ROADS:

  • Masonic Home Road: Started mid-October 2018
  • Old Worcester Road: Started early November 2018

TRAFFIC CONTROL MEASURES: Period Dec. 3, 2018 – Dec. 14, 2018

  • Work will continue occasionally on Masonic Home Road with traffic detoured in both directions. Detail officers are at each end assisting people, school busses, daily deliveries and sanitary services to properties on either side of the work zone.
  • Once the work is complete on Masonic Home Road, the crew will be moving to Old Worcester Road.
  • The work on Old Worcester Road will continue near Main Street and progress easterly.
  • Traffic on Old Worcester Road is being fully detoured. Detail officers are controlling traffic flows from both directions for residents, school busses, daily deliveries and sanitary services to be able to access properties from either side of the work zone.
  • The map below depicts impacted roads (orange), work zones (red), and suggested travel routes during construction (green).

CLICK TO VIEW LARGER MAP

WEEK OF NOVEMBER 12, 2018

The Charlton Waterline Project water main construction will continue along Masonic Home Road and onto Old Worcester Road, as weather conditions permit. Water main construction will cease upon the first snow fall and will resume in April 2019.

IMPACTED ROADS:

  • Masonic Home Road: Started in mid-October 2018
  • Old Worcester Road: Starting in early November 2018
    • HOLIDAY | No waterline construction will take place on Thanksgiving or the day following.

TRAFFIC CONTROL MEASURES: Period Nov. 12, 2018 – Dec. 3, 2018

  • Construction crews will continue working on Masonic Home Road while other crews get work underway on Old Worcester Road. For a short duration, work will occur on both roads.
  • Work on Old Worcester Road will begin at Main Street and progress easterly along the road.
  • Traffic on Old Worcester Road is being fully detoured. Detail officers will control traffic flows from both directions for residents to be able to access their properties from either side of the work zone.
  • The map below depicts impacted roads (orange), work zones (red), and suggested travel routes during construction (green).

CLICK TO VIEW LARGER MAP

 

WEEK OF OCTOBER 1, 2018

The Charlton Waterline Project water main construction will begin along Masonic Home Road before moving to Old Worcester Road, as weather conditions permit. Water main construction will cease upon the first snow fall and will resume in April 2019.

IMPACTED ROADS:

  • Masonic Home Road: Starting in mid-October 2018
  • Old Worcester Road: Starting in early November 2018

TRAFFIC CONTROL MEASURES: Period Oct. 1, 2018-Nov. 12, 2018

  • Masonic Home Road will remain open to all thru traffic during construction. Construction management controls will manage traffic flow.

 

Road travel impacts will be regularly updated on the www.ourcharltoncommitment.com as they become available. Share traffic concerns regarding the construction at: charltoninfo@exxonmobil.com.